Maine's Department of Energy Resources released the state's first competitive solicitation for energy storage on Nov. 19, seeking 200 to 300 megawatts of new capacity and capping purchases at 360 megawatts.

Proposals are due by 3:00 p.m. Eastern time on Friday, Feb. 19, 2027, according to the department's solicitation page. Bidders must request submission instructions by Friday, Feb. 5, 2027, to get access to the secure submission portal. A bidders' conference is set for Thursday, Dec. 3, 2026, from 2:00 to 3:30 p.m. on Zoom. Questions are due Friday, Jan. 8, 2027, the department will answer by Friday, Jan. 22, 2027, and it expects provisional selections in June 2027. The page says the dates are subject to change and that amendments and a question-and-answer log will be posted there.

The department says 360 megawatts equals about 15 percent of Maine's peak electricity demand. The procurement is the first the department has conducted under a new legislative responsibility to lead competitive energy procurements. It may buy more or less than the 200-to-300-megawatt target, up to 360 megawatts, or none at all, and it will select only projects whose expected benefits to Maine ratepayers exceed their costs.

Proposals that meet that test will be evaluated against the department's statutory objectives under 35-A M.R.S. section 10313: benefits of renewable and clean energy to ratepayers, Maine's greenhouse gas reduction obligations, economic and workforce development goals, minimizing environmental impacts, protecting low-income ratepayers, and avoiding or minimizing curtailment of other renewable or clean energy resources. Project safety, viability and other factors will also be considered.

Selected projects would enter contracts of up to 20 years with Central Maine Power or Versant Power. The department says the solicitation supports the statutory goal of installing at least 400 megawatts of energy storage in Maine by 2030. Questions go to rfp.doer@maine.gov.