Providence is asking the City Council to approve $282,000 more for the Trinity Repertory Company's Lederer Theater Center project, covering about half of $564,459 in added costs on the Adrian Hall Way public space. The council's Special Committee on Ways and Means takes up resolution 54944 on Nov. 10 at 5:30 p.m. in Committee B on the third floor of City Hall.
In a Sept. 22 letter to the Board of Contract and Supply, the mayor's office said the city and Trinity Rep each pay 50% of project costs under a partnership agreement approved Feb. 9, 2026. The agreement set the city's amounts at $1,575,000 for fiscal 2026 and $1,650,000 for fiscal 2027, or $3,225,000 combined. The amendment raises the ceiling to $3,507,000, an increase of about 8.7%. The letter says money is available in the account named.
Where the added cost came from
The letter attributes the $564,459 to "water-utility overruns" and attaches an itemized list. The three largest lines are:
Line stops installation: $171,032
Changes to a manhole "doghouse" (labeled "SMH-2 Doghouse") and a 12-inch drain: $86,098
Providence Water test pits: $78,018
Those three come to $335,148, or about 59% of the total. The other seven lines add $229,311 and include repair of a collapsed underground sanitary line ($20,204), removal of excess soil ($50,384), a state Department of Environmental Management soils consultant ($28,900), and "Utility relocation, additional CA, survey for skate park" ($32,892). A draft change order from Gilbane, the contractor, to Trinity Rep says the site contractor found an existing clay sewer pipe collapsed on April 7, 2026, while preparing to install a trench box.
The sewer repair, soil removal, consultant and skate park survey lines do not obviously fit the letter's "water-utility" description, and the packet does not explain how they were grouped under it. It also does not show who approved each charge or whether the full $564,459 has already been paid.
Why the council votes
A Sept. 30 letter from the city's internal auditor asks that the request go to the council and its Finance Committee to determine whether it amends the capital improvement plan ordinance (2026-29, No. 249), which would require a majority vote of the council. The capital improvement plan is the city's list of funded construction projects. The resolution was introduced Oct. 15 and referred to committee.