The Rhode Island Public Utilities Commission (PUC) will take public comment at 6 p.m. on Thursday, Dec. 3, on a proposed 208-megawatt battery energy storage facility in the Quonset Business Park in North Kingstown. The hearing is at the PUC, 89 Jefferson Blvd., Warwick, with a Zoom option and a live stream, according to the PUC's Nov. 20 notice. The notice says bags are not allowed in the hearing room.
Written comments can be sent to Commission Clerk Stephanie De La Rosa at the PUC's Warwick address or at stephanie.delarosa@puc.ri.gov. The notice gives the Zoom link and phone number for remote comment, and the filings are on the PUC's docket page (Docket 26-31-EL).
What is proposed
The Quonset Development Corporation and GDQ ESS, LLC filed the application on Jan. 23, 2026, with an application prepared by Green Development, LLC, the notice says. It describes a facility on about 10 acres inside the business park. The batteries are lithium iron phosphate, outdoors, on about 4.7 acres where the North Kingstown fire station now stands.
The project also includes a substation and a transmission connection: about 2,500 feet of underground 115-kilovolt circuits along Callahan Road, about 500 feet of new above-ground 115-kilovolt circuits owned by Rhode Island Energy that would tie into existing lines south of Route 403, and a switchyard linking the two.
What the PUC is deciding
The PUC is not deciding whether the project gets a license. The Energy Facility Siting Board asked the PUC on Aug. 25 for an advisory opinion on need and cost-justification, including whether the facility would deliver energy at the lowest reasonable cost compared with other reasonable alternatives and comply with the Act on Climate and the State Energy Plan. That opinion is due Feb. 19, 2027, and the notice says it is not a final decision on the project.
After the Dec. 3 comment hearing, the procedural schedule calls for intervenor and Division of Public Utilities and Carriers direct testimony on Dec. 16, applicant rebuttal on Jan. 13, 2027, and an evidentiary hearing starting Jan. 20, 2027, with Jan. 21 and 22 held if needed.
Who has joined the case
The procedural schedule set an Oct. 30 intervention deadline. The Town of North Kingstown filed a motion to intervene on Nov. 20, after the Oct. 30 deadline, and asks the PUC to allow late intervention for good cause.
The town's motion says the project affects services run by its fire, police and public works departments and its municipal golf course, and that a town public works facility and the golf course both abut the site. It says no existing party directly represents the municipal interests of North Kingstown residents.
In pre-filed testimony dated Oct. 23, Quonset Development Corporation Chief Operating Officer Chelsea Siefert said the battery portion is proposed for a parcel that most recently served as the Revolution Wind construction laydown yard and that the battery portion also includes the current North Kingstown fire station site. She said the corporation makes payments in lieu of taxes and the town provides fire, emergency and police services to the business park. The testimony is in the docket.