The Route 164 closure and detour in Caribou will remain in place through winter and spring, the Maine Department of Transportation said Nov. 17, after supplier delays pushed back the Prestile Brook Bridge replacement.

The detour was established July 20, with reopening expected Nov. 20, according to a MaineDOT release. The department said delays in fabricating and delivering precast box sections "significantly affected" the construction schedule, and that the extent of the delays and the approaching winter made the longer closure necessary.

The contractor, McGillan Construction of Fort Fairfield, expects to begin placing the precast box sections by the end of November and to keep working as long as the weather allows. Work will pause when freezing temperatures or snow stop progress. The company is expected to return in the spring to finish the remaining work, and the goal is to complete the whole project by early summer 2027.

The project replaces the existing Prestile Brook Bridge with a large culvert structure. MaineDOT said the aims are to improve fish and wildlife habitat and to reduce collisions between wildlife and vehicles. The project is supported by a Federal Highway Administration Wildlife Crossings Pilot Program grant.

The release gives no new reopening date. It says only that the closure and detour are expected to remain through winter and spring. MaineDOT asked motorists and pedestrians to keep following the posted detour signs and to use caution in the detour area. Message boards will continue to carry information about the closure. The release did not give the detour route, the project's cost or any change in cost from the delay.