An engineer retained by New Hampshire's Counsel for the Public told the Site Evaluation Committee on Nov. 6 that Eversource has not shown a full rebuild of its X-178 transmission line is justified, and that it has not provided third-party inspection reports for the poles it wants to replace.
James M. Orosz, a licensed electrical engineer with Robson Forensic, filed prefiled direct testimony and a 13-page technical review report in docket SEC 25-072. Eversource (Public Service Company of New Hampshire) applied Nov. 18, 2025, to replace the wood structures on the 115-kilovolt line between the Beebe River Substation in Campton and the Whitefield Substation in Whitefield with steel structures, and to install larger conductors and a fiber-optic ground wire.
What Orosz concluded
Eversource says 158 structures on the line need immediate replacement. Orosz wrote that the company gave drone photographs of those poles but not detailed inspection reports from the third parties that examined the line, so he could not assess whether the 158 figure is accurate. He noted that tags visible in the company's photographs show the poles were inspected by a third party over the years.
He also pointed to maintenance records Eversource filed. A forced-outage report in the record shows six wooden-structure repairs on the line between 2006 and 2022, he wrote, which makes it surprising that so many poles are now rated in poor condition. In his opinion, Eversource "has not adequately maintained" the line and has used its condition to justify the project. That is Orosz's opinion; the committee has made no finding.
His report listed three findings, each offered "within the bounds of reasonable engineering certainty." Eversource has not demonstrated a comprehensive analysis of alternatives, he wrote. It has not shown the project's cost is worth its benefits. And it has not demonstrated it can operate and maintain the existing line to the National Electrical Safety Code and industry standards of care.
Orosz wrote that Eversource has said it does not plan to increase the line's capacity, and that the company has not quantified the benefit of larger conductors or of the fiber-optic wire. He said the company has not presented a net present value comparison of the rebuild against keeping the wood poles. He testified that a wood-pole line can continue to provide reliable service if properly inspected and maintained, and that steel poles require heavier equipment and concrete foundations.
On the safety code, Orosz testified that a provision, Section 013.B.2, exempts older lines built to code from newer standards, so an in-kind replacement does not require the line to meet recent changes.
Eversource's case
The application, as quoted in Orosz's report, says Eversource considered three smaller alternatives through the regional grid operator's planning process and chose the full rebuild. It says replacing structures in stages would require repeated access to the right of way, and that the rebuild would address asset condition and reliability risks and add a fiber path to northern New Hampshire. The company wrote that the upfront cost of a full rebuild may be greater but that addressing all structures at once would be the most cost-effective.
Eversource's rebuttal testimony is due Jan. 5, 2027, under the committee's schedule.
Motion to compel inspection reports
On Nov. 13, intervenor Kris Pastoriza asked Presiding Officer Mark Dell'Orfano to order Eversource to produce the third-party inspection reports Orosz refers to, or to state that none exist. Pastoriza wrote that Osmose may have produced inspection reports in 1982, 1991, 2001, 2011 and 2019 for one segment of the line and in 2001, 2011 and 2019 for two others. Those years are her estimate, not a finding.
The motion says the Town of Easton assents and Counsel for the Public takes no position. It says Eversource had not responded. Dell'Orfano denied an earlier Pastoriza motion for production of structure inspections on Oct. 2.
Schedule
Under the Oct. 5 order, parties had until Nov. 20 to serve data requests on Counsel for the Public, and state agencies' final permits and conditions are due Nov. 25. A technical session is set for Dec. 16. The final adjudicative hearing is scheduled for Feb. 18, Feb. 19, March 1 and March 5, 2027, with public deliberations March 15 to 17. A final order is due by March 31, 2027, unless the committee suspends its deliberations. The presiding officer can change the schedule.
The existing line has 594 structures, 580 of them wood and 14 steel, according to Orosz's report. It runs through Campton, Thornton, Woodstock, Lincoln, Easton, Sugar Hill, Bethlehem, Dalton and Whitefield, and 117 of its structures are in the White Mountain National Forest.
Sources: N.H. Site Evaluation Committee docket SEC 25-072: Order Adopting Final Procedural Schedule, Oct. 5, 2026; prefiled direct testimony of James M. Orosz, Nov. 6, 2026; Orosz technical review report, Nov. 5, 2026; Pastoriza motion to compel, Nov. 13, 2026; order denying Pastoriza motion, Oct. 2, 2026.