The Connecticut Department of Transportation will present its plan to remove two traffic signals from Route 9 in downtown Middletown at a public information meeting on Wednesday, Nov. 18. An open house starts at 5:30 p.m. and the formal presentation at 6:30 p.m. at Middletown High School, 200 La Rosa Lane. The agency's public notice puts the estimated construction cost of the two linked projects at $143 million, 80 percent federal money and 20 percent state money.
The signals sit on a 0.36-mile stretch of Route 9 that is otherwise a freeway. CTDOT's project description reports 574 crashes with 183 injuries on Route 9 within the project limits from Jan. 1, 2022, through Dec. 31, 2024, and says the Hartford Avenue intersection at Exit 24 is on the department's High Frequency Crash List. That intersection is the main link between Route 9 and the Arrigoni Bridge to Portland.
Under the plan, a new northbound off-ramp at River Road, ending at a three-leg roundabout, would become the main exit for drivers headed downtown. The ramp requires a partial acquisition of a Superfund site owned by RLO Properties, along with minor acquisitions of city property, according to the project description. The Exit 24 signal would go, and northbound access from Route 9 to Hartford Avenue would end. At the Washington Street interchange, the signal would go and access to Washington Street from both directions of Route 9 would end, while access to Route 9 southbound would stay with a new acceleration lane.
The companion project, 0082-0330, would make Rapallo Avenue one-way toward Main Street. CTDOT says the change keeps all 21 on-street parking spaces. Northbound trucks bound for the Arrigoni Bridge would be encouraged to leave at Exit 25 in Cromwell, where a roundabout is proposed at Route 99, and reverse direction. The department says that route is two minutes longer than using the new River Road ramp.
The records give different start dates. The public notice says construction is expected to start in spring 2027, depending on funding, right-of-way acquisition and permits. The project description, revised Aug. 17, lists a spring 2028 start and a fall 2031 finish, subject to funding. The project page for project 0082-0318 lists design completion on May 26, 2027, advertising on June 23, 2027, an award on Sept. 17, 2027, and notice to proceed on Nov. 1, 2027. The page says state and federal permit reviews of up to 18 months extended the design phase by about a year, with permits expected in July 2027. The page for the Rapallo project lists a May 31, 2027 notice to proceed, subject to funding.
CTDOT says it has been interested in removing the signals since the early 2000s and that public meetings in 2016 and 2018 and workshops on alternatives in 2024 preceded this one. The design now on the table is labeled Alternative 11 on the meetings page. The meeting will be recorded and posted, and comments can go to DOT.Rte9Middletown@ct.gov.