The Maine Department of Transportation opened the new Tuttle Road Bridge in Cumberland to traffic in both directions on Nov. 18, 2026.
The bridge carries Tuttle Road over Interstate 295, U.S. Route 1 and state-owned railroad tracks, connecting Foreside Road and Route 1 with Middle Road, MaineDOT said in a Nov. 19 release.
The department built the new bridge alongside and to the north of the existing one. That let drivers keep using the old bridge during most of construction and avoided an extended closure of the local connection, the department said.
MaineDOT said the old structure was built in 1959 and had preservation work in 1990. The new bridge has two 11-foot travel lanes and five-foot shoulders. MaineDOT said it will include a six-foot sidewalk.
With traffic using the new bridge, crews will begin demolishing the old structure over the winter. The sidewalk, final paving of the approaches and other finishing work are scheduled for spring and summer 2027. MaineDOT asked drivers to use caution around crews and equipment, noting that the opening does not end construction.
Reed & Reed of Woolwich, Maine, is the contractor. The construction contract is worth about $12.9 million, according to the department.
The release does not say whether the sidewalk will be open to pedestrians before it is finished, or whether lane restrictions are planned during demolition over I-295 and Route 1.