The Public Utilities Commission will vote Wednesday, Nov. 18, on Westerly's request for more time to launch the community electricity aggregation plan the commission approved in 2024, according to the commission's open meeting notice. The state Division of Public Utilities and Carriers recommended in a Nov. 9 memo that the deadline be extended to Oct. 1, 2028, with a status report due within 12 months of the extension order.
The meeting starts at 11:30 a.m. in Hearing Room A at 89 Jefferson Blvd. in Warwick. The commission will not take oral public comment because the session is not a hearing.
The commission approved the plan Oct. 1, 2024, and issued Order No. 25185 on Nov. 6, 2024, requiring the town to report within two years on whether it had been implemented. In a Sept. 30 notice filed by its consultant, Freedom Energy Logistics, the town said no customers have been enrolled and no retail electric supply is being provided through the program. The notice lists what remains undone: a competitive solicitation for supply, a supply agreement, a launch date and final pricing, and customer education and opt-out notices.
A footnote in the commission's Oct. 7 memo says this is the first time a municipal aggregation plan has not been implemented within the two-year period. State law lets the commission allow further time and also says it may revoke certification of a plan if the municipality fails to substantially implement it, according to the memo, which quotes the statute. The memo adds that the law sets no specific standard for granting more time.
The memo asked the town to confirm its aggregator, because the last filing named Colonial Power Group, and to say whether the Town Council had acted on the plan. The Division reported that the town manager confirmed Freedom Energy Logistics is the current consultant and provided a novation agreement documenting its substitution for Colonial Power. It also reported that the Council considered implementation in 2025 but did not authorize a launch, and that the town is considering implementation in 2027, depending on Council direction and market conditions.
The Division found no present harm to residents from keeping the plan authorized. An extension would not change any customer's supplier, rate or billing, the memo says, and would not itself authorize a launch or waive customer-notice requirements. It also says the consultant's management fee is tied to electricity purchased by participating customers and is paid by the selected supplier, so keeping the authorization in place does not trigger it. The earlier indicative prices and projected savings cannot stand in for disclosures at an actual launch, the Division wrote.
The matter is Docket 24-24-EL.