A Providence school facilities plan would temporarily relocate Roger Williams Middle School students for approximately two years while creating a combined pre-K-through-eighth-grade campus with Young Woods Elementary School.

The district has posted an October 2026 report. It describes a model in which Young Woods would serve pre-K through second grade, including 10 pre-K classrooms, and the renovated Roger Williams building would serve third through eighth grades.

The proposed work includes accessibility improvements, an elevator, replacement of aging building systems, hazardous-material removal, and classroom and technology upgrades. The report targets a July 2027 construction start at Roger Williams and occupancy in August 2029.

Young Woods work is targeted to start in July 2028 and finish in December 2028. Its students are expected to remain at the school while sections of the building are separated for construction. The report says work would occur mainly in summer, though its schedule extends through December 2028.

A Sept. 10 budget planning sheet included in the report lists approximately $104.6 million as total construction cost across Roger Williams, Young Woods and site work. The estimate includes scope reductions, including no new Young Woods roof and no new kitchen. It is a planning estimate, rather than a final contract or a verified all-in financing figure.

The family transition plan does not identify the temporary school site for Roger Williams students. It says middle school students living at least 1.5 miles from that location would qualify for transportation under district policy.

After the proposed merger, rising sixth graders could seek a different middle school through the standard district school-choice lottery. The report identifies the merger as proposed and does not establish the current approval status or a vote date.